Sprint board and burndown
Sprint board và Burndown
Visualise & Explore
· Trực quan hóa & Tương tácJira sprint board & burndown dynamics
Bảng Jira Sprint & Biểu đồ Burndown
Reconstructed from P4 · Page 15
Tái dựng từ P4 · trang 15
Sprint Burndown (D1–D10, 30 pts): a flat start indicates too much work pulled in parallel or an unreported blocker.Burndown (D1–D10, 30 điểm): đường đi ngang lúc đầu báo hiệu ôm quá nhiều việc song song hoặc có trở ngại chưa báo cáo.
Backlog: WMS-31 Cycle-count screen (8), WMS-34 Putaway suggestion (13). In Progress (WIP limit 1/person): WMS-28 Barcode scan on receipt (5, Linh). Review (bottlenecks form here): WMS-25 Stock report export (3, Dũng). Done: WMS-21 Login & roles (5, Mai), WMS-22 Item master import (8, Mai). Definition of Done: Coded, code-reviewed, tested, documented, deployed to staging. Flat burndown start signals excessive WIP or unreported blocker.
Understand
· Giải thích khái niệmBacklog: WMS-31 cycle count (8), WMS-34 put-away (13). In progress: WMS-28 barcode receipt (5, Linh). Review: WMS-25 stock report export (3). Done: WMS-21 login/roles (5, Mai), WMS-22 item import (8, Mai). WIP limit one per person; review may be the bottleneck. A flat early burndown may signal too much parallel work or a blocker. Definition of Done: coded, code-reviewed, tested, documented and deployed to staging.
WIP limit on the board: one active item per person. The Review column is where bottlenecks commonly form. Definition of Done must be written down explicitly: coded, code-reviewed, tested, documented and deployed to staging.
WMS-25 stock report export is in Review and assigned to Dũng in the slide. Planning/estimation is relative; the source stresses that the discussion is the value of Planning Poker, not the number alone.