Cutover weekend
Kịch bản cuối tuần Go-live & Cổng Go / No-Go
Understand
· Giải thích khái niệmFriday 18:00 freeze (announce one week ahead), 20:00 full stock count. Saturday 08:00 extract/cleanse, 14:00 load, 20:00 reconcile counts, totals and a 50-item sample. Sunday 08:00 smoke test one transaction of each type, 14:00 go/no-go, 16:00 open with support. Monday 06:00 first real shift, super-users in every zone. All four gates must pass: reconciliation within tolerance, smoke tests passed, staffed support and tested/ready rollback. An unrehearsed rollback is not ready.
Notify users one week ahead of the legacy freeze; perform a smoke test executing one of every transaction type; assign super-users in every zone for the first shift. All four Go/No-Go gate checks must pass — not some.
The full stock count establishes closing balances. The 08:00 Saturday step is extraction and final cleansing; Sunday opening has support on site.