11.4 · Training & Post-Go-liveConcept 13/15
Source: P4 · p. 36Case studies: Hershey and Vietnamese WMS
Case Hershey và WMS VN
Understand
· Giải thích khái niệmHershey 1999: big bang ERP + CRM + SCM, compressed schedule and testing, go-live before Halloween peak; could not fulfil retailer orders, revenue/share price fell. Vietnamese WMS: pilot one warehouse for two months, train five long-serving staff, clean data and launch in low season; fast adoption, fewer tickets after week two, four weeks hypercare then phased rollout. Discuss which single decision Hershey could change.
VIHershey 1999 ERP+CRM+SCM big bang, timeline rút/testing cắt, pre-Halloween peak; không fulfil retailer orders, doanh thu/cổ phiếu giảm. WMS VN pilot kho 2 tháng, train 5 staff lâu năm, clean data, low season; adoption nhanh, ticket giảm sau tuần 2, hypercare 4 tuần rồi phased. Thảo luận nếu Hershey đổi một quyết định?